Haryana Rera orders refund with interest in BPTP Terra case, rejects limitation plea

Haryana Rera has ordered BPTP Limited to refund Rs 18.12 lakh with 2% interest to a homebuyer for its Park Terra project. The developer's claim that the complaint was time-barred was rejected, as Rera cited a continuing breach of contract. The authority also noted BPTP's attempt to forfeit more than the permissible earnest money, violating Rera provisions.

PNSPNS
Mar 30, 2026 - 12:46
 0
Haryana Rera orders refund with interest in BPTP Terra case, rejects limitation plea
Haryana Rera has ordered BPTP Limited to refund Rs 18.12 lakh with 2% interest to a homebuyer for its Park Terra project. The developer's claim that the complaint was time-barred was rejected, as Rera cited a continuing breach of contract. The authority also noted BPTP's attempt to forfeit more than the permissible earnest money, violating Rera provisions.